Earned Value Management (EVM) as a Real-Project-Based Learning Resource in Construction Management: A Quantitative-Descriptive Study on a Revetment Construction Project

Authors

DOI:

https://doi.org/10.61255/jupiter.v4i2.983

Keywords:

Earned Value Management, Construction Management, Project-Based Learning, Revetment, Project Control

Abstract

Purpose: This study assesses the project performance of a revetment construction project at Manado Bay, Bersehati Market Complex (contract value IDR 11,120,996,728; duration 133 calendar days) using the Earned Value Management method, while examining its effectiveness as a real-project-based learning medium in the Construction Management course. Methods: A quantitative-descriptive approach using Earned Value Analysis was employed over 19 weeks, applying three primary EVM indicators BCWS, BCWP, and ACWP, from which SPI, CPI, and project completion projections (ETC, EAC, ETS, ECD) were derived from the project's BoQ, planned and actual S-curves, and weekly execution reports. Findings: At week 19, SPI = 2.6 (ahead of schedule) and CPI = 0.4 (severe cost overrun). EAC reached IDR 50,896,353,625.36 (≈4.6× the original budget); estimated completion is 167 days, exceeding the contract by 34 days. The paradoxical coexistence of high SPI and critically low CPI constitutes an educationally valuable scenario for analytical learning. Research Implications: Real project data has strong potential to strengthen students’ conceptual understanding of EVM, cultivate integrated data-interpretation skills, and build forecasting competencies aligned with construction industry demands. Civil engineering programs should systematically incorporate real project case studies supported by comprehensive assessment rubrics. Conclusion: EVM analysis of real government project data constitutes an effective and theoretically grounded PBL medium for Construction Management instruction, simultaneously developing technical competency and higher-order analytical thinking aligned with KKNI Level 6 and SN-Dikti requirements. Originality: This study is the first to integrate quantitative EVM project-performance analysis with a theoretically grounded pedagogical framework within a single coherent research design, addressing a gap in civil engineering education literature in Indonesia.
Abstract views: 1 , PDF downloads: 0

Downloads

Download data is not yet available.

References

Acebes, F., Pajares, J., Galán, J. M., & López-Paredes, A. (2021). Beyond earned value management: A graphical framework for integrated cost, schedule and risk monitoring. Procedia Computer Science, 181, 687–694. https://doi.org/10.1016/j.procs.2021.01.219

Aramali, V., Gibson, G. E., El Asmar, M., Cho, N., & Sanboskani, H. (2022). Forward-looking state-of-the-art review on earned value management systems. Journal of Management in Engineering, 38(3), 03122001. https://doi.org/10.1061/(ASCE)ME.1943-5479.0001019

Bonato, J., Steinhauer, H. J., & Sikander, E. (2020). An application of Earned Value Management (EVM) with Monte Carlo simulation in engineering project management. International Journal of Project Management, 38(5), 310–323.

Chen, C. H., & Yang, J. C. (2019). Revisiting the effects of project-based learning on students’ academic achievement: A meta-analysis investigating moderators. Educational Research Review, 26, 71–81. https://doi.org/10.1016/j.edurev.2018.11.001

Chen, J., Kolmos, A., & Du, X. (2021). Forms of implementation and challenges of PBL in engineering education: A review of literature. European Journal of Engineering Education, 46(1), 90–115. https://doi.org/10.1080/03043797.2020.1718615

Dewi, N. (2018). Studi penggunaan metode EVM (Earned Value Management) pada pengendalian biaya dan waktu proyek pembangunan Mall Grand Dayasquare.

Domu, I., & Mangelep, N. O. (2023). Developing mathematical literacy problems based on the local wisdom of the Tempang community on the topic of space and shape. AIP Conference Proceedings, 2621. https://doi.org/10.1088/1742-6596/1387/1/012135

Durdyev, S. (2021). Review of construction journals on causes of project cost overruns. Engineering, Construction and Architectural Management, 28(4), 1241–1260. https://doi.org/10.1108/ECAM-02-2020-0137

Kawet, R. S. S. I. (2023). Analisis perbandingan perhitungan gaya-gaya dalam program SAP2000 v21 dengan metode matriks kekakuan pada gedung rumah susun mahasiswa Universitas Negeri Manado. Jurnal Ilmiah Media Engineering, 13(1), 43–50. https://doi.org/10.35793/jime.v13i1.49228

Kawet, R. S. S. I., & Kojo, R. (2024). Analisis tingkat kecelakaan lalu lintas pada ruas jalan penghubung Desa Kolongan Atas dan Desa Leilem dengan metode angka ekivalen kecelakaan (AEK). TEKNO: Jurnal Teknologi Elektro Dan Kejuruan, 22(87). https://doi.org/10.35793/jts.v22i87.54071

Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (12th ed.). Wiley.

Kokotsaki, D., Menzies, V., & Wiggins, A. (2016). Project-based learning: A review of the literature. Improving Schools, 19(3), 267–277. https://doi.org/10.1177/1365480216659733

Krajcik, J. S., & Shin, N. (2014). Project-based learning. In R. K. Sawyer (Ed.), The Cambridge Handbook of the Learning Sciences (2nd ed., pp. 275–297). Cambridge University Press.

Mangelep, N. O. (2017). Pengembangan perangkat pembelajaran matematika pada pokok bahasan lingkaran menggunakan pendekatan PMRI dan aplikasi Geogebra. Mosharafa: Jurnal Pendidikan Matematika, 6(2), 193–200. https://doi.org/10.31980/mosharafa.v6i2.306

Mangelep, N. O. , Mahniar, A. , A. I. , & Rumintjap, F. O. (2024). Fuzzy simple additive weighting method in determining single tuition fees for prospective new students at Manado State University. Innovative: Journal Of Social Science Research.

Mangelep, N., Sulistyaningsih, M., & Sambuaga, T. (2020). Perancangan Pembelajaran Trigonometri Menggunakan Pendekatan Pendidikan Matematika Realistik Indonesia. JSME (Jurnal Sains, Matematika & Edukasi), 8(2), 127–132.

Narbaev, T., & De Marco, A. (2014). An earned schedule-based regression model to improve cost estimate at completion. Journal of Modern Project Management, 2(1), 32–39. https://doi.org/10.19255/JMPM00402

Pramesti, A. (2019). Manajemen Proyek Konstruksi: Konsep, Tahapan, dan Implementasi. Penerbit Teknik.

Sholahuddin, M., & Saputra, I. H. (2024). Penerapan Earned Value Management (EVM) sebagai upaya pengendalian kinerja biaya dan waktu pelaksanaan pada pekerjaan infrastruktur jalan. Innovative: Journal of Social Science Research, 4(5), 3353–3366. https://doi.org/10.31004/innovative.v4i5.14896

Downloads

Published

2026-05-14

How to Cite

S. S. I. Kawet, R., & Mangelep, N. O. (2026). Earned Value Management (EVM) as a Real-Project-Based Learning Resource in Construction Management: A Quantitative-Descriptive Study on a Revetment Construction Project. Jurnal Pendidikan Terapan, 4(2), 258–267. https://doi.org/10.61255/jupiter.v4i2.983

Issue

Section

Articles